Lift Co-Pilot

BS 7121-1 · LOLER 1998 · CIRIA C703

Awaiting input

Point the rear camera at the pick-up zone and landing bay to capture site evidence for the lift plan.

Pick-up zone · not captured
Landing bay · not captured
01

Voice briefing

en-GB · regex parse
Speech is processed by your browser; text can also be typed.
02

Load & geometry

Gross load build-up
Net load0.000 t
Contingency (10%, estimated weight)0.000 t
3-sheave hook block0.350 t
Slinging gear / accessories0.120 t
Gross load on hook0.470 t
03

Duty chart solver

Liebherr LTM 1060-3.1
12.8 t CW · 6.3 m base 100%
Boom length
–m
Working angle
–°
Chart capacity
–t
Utilisation
–%
0%75%90%100%
BoomAngleTip htCap.Util.Status
Engine constants

Capacities are read conservatively at the next greater tabulated radius (no interpolation). Chart values are indicative for planning and must be verified against the crane's on-board LICCON load chart and the manufacturer's current tables before lifting.

04

Outrigger & ground bearing

CIRIA C703 · FoS 1.25
Pmax outrigger
–kN
Allowable q
–kPa
Area required
–m²
Applied q (mat)
–kPa
–Standard stock spreader mat, one per outrigger.

Pmax = Gross load (kN) + 0.65 × total crane deadweight (kN). Allowable bearing = presumed bearing ÷ 1.25.

05

Job & lift team

Lift plan header
06

RAMS — generated controls

Condition-driven
    07

    Appointed Person gateway

    CPCS A61 · LOLER Reg. 8
    AP signature
    Sign above · Appointed Person
    Draft · not authorisedComplete all gateway items to authorise.
    Important: This tool is a planning aid. Duty chart data is an indicative model of the Liebherr LTM 1060-3.1 (12.8 t counterweight, 6.3 m outrigger base, 100% extension) and ground figures are presumed values. Every lift plan must be reviewed and authorised by a competent Appointed Person under BS 7121-1 and LOLER 1998 before any lifting operation proceeds. Form data is saved on this device only.